Before and after Ola Adua Culvert

Project Overview

The Four Priority Sites were the first set of hydraulic structures identified to be so badly hit by the flood event of August 26, 2011, on account of which IUFMP became a necessity. They were located at areas where residents were mostly cut off as a result of the devastating effects of the flooding. The works took the form of constructing vastly adequate hydraulic structures to replace the damaged ones for the purpose of flood control, whilst also helping to reconnect the disconnected locations.

Project Scope

Four Priority Sites

  1. Ola Adua 3-Cell Culvert, Apete, Ido LGA.
  2. Saasa-Osajin 2-Cell Culvert, Apete, Ido LGA.
  3. Cele-Rainbow 3-Cell Culvert, Ajakanga Road, Oluyole LGA.
  4. Ogbere Pegba 2-Span x 15m Bridge, Egbeda Tuba Road, Oluyole LGA.

Subsequently, there was an extension of works at the 4 priority sites, essentially to open up adjoining areas and link up the channel to other network of channels.

Project Type:

Construction

Project Status:

Completed

Project Date:

to

Document Library

Final Report
Title File Doc. ID Access
Environmental and Social Management Plan ESMP for the Reconstruction of the Ola Adua Culvert Environmental and Social Management Plan ESMP for the Reconstruction of the Ola Adua Culvert Adeleru,Ruth Adetola.
Nigeria - Ibadan Urban Flood Management Project : environmental assessment (Vol. 3) : Environmental and social management plan for the reconstruction of the Ola Adua Culvert (English). Washington, D.C. : World Bank Group.
Environmental and Social Management Plan ESMP for the reconstruction of the Cele-Rainbow - Ojoekun - Ajanaku way- Agara Culvert Environmental and Social Management Plan ESMP for the reconstruction of the Cele-Rainbow - Ojoekun - Ajanaku way- Agara Culvert Adeleru,Ruth Adetola.
Nigeria - Ibadan Urban Flood Management Project : environmental assessment (Vol. 2) : Environmental and social management plan for the reconstruction of the Cele-Rainbow - Ojoekun - Ajanaku way- Agara Culvert (English). Washington, D.C. : World Bank Group.
Environmental and Social Management Plan for the Reconstruction of the Ogbere Pegba - Egbada Tuba Road - Pegba (Ogbere River) Bridge Environmental and Social Management Plan for the Reconstruction of the Ogbere Pegba - Egbada Tuba Road - Pegba (Ogbere River) Br Adeleru,Ruth Adetola.
Nigeria - Ibadan Urban Flood Management Project : Environmental Assessment : Environmental and social management plan for the reconstruction of the Ogbere Pegba - Egbada Tuba road - Pegba (Ogbere river) bridge (English). Washington, D.C. : World Bank Group.
Environmental and Social Management Framework ESMP for the reconstruction of the Saasa River Culvert, Apete Road-Osajin Environmental and Social Management Framework ESMP for the reconstruction of the Saasa River Culvert, Apete Road-Osajin
Completion Level
100%